NOTICE:  Clearwave Fiber has stated working as part of their fiber build in Godfrey.  Below proposed working schedule:

The Week of 05/25/23 (Thursday)

  • Work on Summerfield Subdivision (Aster Ln.)
  • Work on Wolferton Dr. & Cavalier Ct.
  • Work on Montclair Ave. Railroad Crossings

The Week of 05/18/23 (Thursday)

  • Work on Summerfield Subdivision (Summerfield Dr., Foxglove Ln. & Vinca Ln.)
  • Work on Ridgefield Dr.
  • Work on Montclair Ave. and Bethany Ln. Railroad Crossings

The Week of 05/11/23 (Thursday)

  • Work on The Oaks at Greystone Subdivision (White Oak Trail, Cedar Creek Ct., Whispering Woods Dr., Woodland Meadows Dr., Laurel Oak Dr. & Ryan Dr.)
  • Work on The Oaks at Deer Creek Subdivision (White Oak Trail, Hawk Ridge Ct., Deer Creek Ct. & Quail Crossing)
  • Work on The Seasons Subdivision (Autumn St., Fall Dr. & Seasons Dr.)
  • Work on Humbert Rd. and Bethany Ln.

The Week of 05/04/23 (Thursday)

  • Work on Enos Ln.
  • Work on Montclair Ave. at RR and Bethany Ln. at RR
  • Work on Humbert Rd.
  • Work on Seasons Subdivision (Autumn St., Fall Dr. & Seasons Dr.)

The Week of 04/27/23 (Thursday)

  • Work on Enos Ln.
  • Work on Montclair Ave., Elizabeth St. and Elizabeth Ct.
  • Work on Humbert Rd.
  • Work on Seasons Subdivision (Autumn St., Fall Dr. & Seasons Dr.)

The Week of 04/20/23 (Thursday)

  • Work on Enos Ln.
  • Work on Montclair Ave., Elizabeth St. and Elizabeth Ct.

The Week of 04/13/23 (Thursday)

  • Work on Enos Ln., Morkel Dr. & Greenwood Ln.
  • Work on Montclair Ave and Montclair Subdivision (Alpine Dr., Cedar Dr., Pinewood Dr., Redwood Dr. & Walnut Dr.)
  • Need to work on Tolle Ln. Railroad Crossing