NOTICE:  Clearwave Fiber has stated working as part of their fiber build in Godfrey.  Below proposed working schedule:

The Week of 08/02/23 (Wednesday)

  • Work on Summerfield Subdivision (Summerfield Ln. & Foxglove Ln.)

The Week of 07/26/23 (Wednesday)

  • Work on Tremont Subdivision (Canary Ln., Chuck Ct., Meadowlark Dr., Nightingale Ln. Redbird Ln., Starling Ct. & Tremont Dr.)

The Week of 07/19/23 (Wednesday)

  • Work on Tremont Subdivision (Canary Ln., Chuck Ct., Meadowlark Dr., Nightingale Ln. Redbird Ln., Starling Ct. & Tremont Dr.)

The Week of 07/12/23 (Wednesday)

  • Work on Tremont Subdivision (Canary Ln., Chuck Ct., Meadowlark Dr., Nightingale Ln. Redbird Ln., Starling Ct. & Tremont Dr.)

The Week of 07/05/23 (Wednesday)

  • Work on Tremont Subdivision (Canary Ln., Chuck Ct., Meadowlark Dr., Nightingale Ln. Redbird Ln., Starling Ct. & Tremont Dr.)

The Week of 06/28/23 (Wednesday)

  • Work on Tremont Subdivision (Canary Ln., Chuck Ct., Meadowlark Dr., Nightingale Ln. Redbird Ln., Starling Ct. & Tremont Dr.)

The Week of 06/21/23 (Wednesday)

  • Work on Straube Ln. & Humbert Rd.Work on Wolferton Dr. & Cavalier Ct. (Structures)
  • Pulling Fibers in some locations

The Week of 06/14/23 (Wednesday)

  • Work on Summerfield Subdivision (Aster Ln.)
  • Work on Wolferton Dr. & Cavalier Ct.
  • Pulling Fibers in some locations

The Week of 06/07/23 (Wednesday)

  • Digging Work on Hold – Pulling Fibers in some locations

The Week of 06/01/23 (Thursday)

  • Work on Hold

The Week of 05/25/23 (Thursday)

  • Work on Summerfield Subdivision (Aster Ln.)
  • Work on Wolferton Dr. & Cavalier Ct.
  • Work on Montclair Ave. Railroad Crossings

The Week of 05/18/23 (Thursday)

  • Work on Summerfield Subdivision (Summerfield Dr., Foxglove Ln. & Vinca Ln.)
  • Work on Ridgefield Dr.
  • Work on Montclair Ave. and Bethany Ln. Railroad Crossings

The Week of 05/11/23 (Thursday)

  • Work on The Oaks at Greystone Subdivision (White Oak Trail, Cedar Creek Ct., Whispering Woods Dr., Woodland Meadows Dr., Laurel Oak Dr. & Ryan Dr.)
  • Work on The Oaks at Deer Creek Subdivision (White Oak Trail, Hawk Ridge Ct., Deer Creek Ct. & Quail Crossing)
  • Work on The Seasons Subdivision (Autumn St., Fall Dr. & Seasons Dr.)
  • Work on Humbert Rd. and Bethany Ln.

The Week of 05/04/23 (Thursday)

  • Work on Enos Ln.
  • Work on Montclair Ave. at RR and Bethany Ln. at RR
  • Work on Humbert Rd.
  • Work on Seasons Subdivision (Autumn St., Fall Dr. & Seasons Dr.)

The Week of 04/27/23 (Thursday)

  • Work on Enos Ln.
  • Work on Montclair Ave., Elizabeth St. and Elizabeth Ct.
  • Work on Humbert Rd.
  • Work on Seasons Subdivision (Autumn St., Fall Dr. & Seasons Dr.)

The Week of 04/20/23 (Thursday)

  • Work on Enos Ln.
  • Work on Montclair Ave., Elizabeth St. and Elizabeth Ct.

The Week of 04/13/23 (Thursday)

  • Work on Enos Ln., Morkel Dr. & Greenwood Ln.
  • Work on Montclair Ave and Montclair Subdivision (Alpine Dr., Cedar Dr., Pinewood Dr., Redwood Dr. & Walnut Dr.)
  • Need to work on Tolle Ln. Railroad Crossing

The Week of 04/06/23 (Thursday)

  • Work on Rosemont Subdivision (Greenleaf Ave. & Rosebud Ln.) and Isabel Dr.
  • Work on South Hanser Ln. & Pear Tree Ln.
  • Work on Humbert Rd.

The Week of 03/30/23 (Thursday)

  • Work on Villa Marie Subdivision (St. Anthony Dr., St. Charles Dr., St. John Dr., St. Joseph Dr., St. Paul Dr., St. Peter Dr., St. Rose Dr., & St. Thomas Dr.) by Priority Line
  • Work on Blu Fountain Dr. by Priority Line
  • Work on Homer Adams Pkwy. & Martin Luther King Dr. by Priority Line

The Week of 03/23/23 (Thursday)

  • Work on Villa Marie Subdivision (St. Anthony Dr., St. Charles Dr., St. John Dr., St. Joseph Dr., St. Paul Dr., St. Peter Dr., St. Rose Dr., & St. Thomas Dr.) by Priority Line
  • Work on W. Delmar Ave. and Blu Fountain Dr. by Priority Line
  • Work on Homer Adams Pkwy. & Martin Luther King Dr. by Priority Line

The Week of 03/16/23 (Thursday)

  • Work on Villa Marie Subdivision (St. Anthony Dr., St. Charles Dr., St. John Dr., St. Joseph Dr., St. Paul Dr., St. Peter Dr., St. Rose Dr., & St. Thomas Dr.) by Priority Line
  • Work on W. Delmar Ave. and D’Adrian Subdivision (Paris Dr., Biscay Dr., & Chateau Dr.) by Priority Line
  • Work on Godfrey Rd. & Airport Rd. by Priority Line
  • Work on Homer Adams Pkwy. & Godfrey Rd. by Priority Line

The Week of 03/09/23 (Thursday)

  • Work on Villa Marie Subdivision (St. Anthony Dr., St. Charles Dr., St. John Dr., St. Joseph Dr., St. Paul Dr., St. Peter Dr., St. Rose Dr., & St. Thomas Dr.) by Priority Line
  • Work on W. Delmar Ave. and D’Adrian Subdivision (Paris Dr., Biscay Dr., & Chateau Dr.) by Priority Line
  • Work on Godfrey Rd. by Priority Line
  • Work on Holland Ave., Chouteau Ave. & West Delmar Ave. by Priority Line

The Week of 03/02/23 (Thursday)

  • Work on St. Joseph Dr., Greenleaf Ave. and Rosebud Ln. by Priority Line
  • Work on W. Delmar Ave. and D’Adrian Subdivision (Paris Dr., Biscay Dr., & Chateau Dr.) by Priority Line
  • Work on Godfrey Rd. by Priority Line
  • Work on Holland Ave. & Chouteau Ave. by Priority Line

The Week of 02/23/23 (Thursday)

  • Work on Hand Dr., St. Ambrose Dr. and Cook St. by Priority Line
  • Work on W. Delmar Ave., Pierce Ln. and D’Adrian Subdivision by Priority Line
  • Work on Lars Hoffman Crossing and Godfrey Rd. by Priority Line
  • Work on Holland Ave. by Priority Line

The Week of 02/16/23 (Thursday)

  • Work on Godfrey Rd. (North of Pearl St.) by Priority Line
  • Work on W. Delmar Ave., Pierce Ln. and D’Adrian Subdivision by Warren Construction
  • Work on Lars Hoffman Crossing and Godfrey Rd. by Priority Line
  • Work on McPherson Ave., Douglas St. & Holland Ave. by Priority Line

The Week of 02/09/23 (Thursday)

  • Work on Godfrey Rd. (North of Pearl St.) by Priority Line
  • Work on W. Delmar Ave., and D’Adrian Subdivision (Work has been Halted) by Warren Construction
  • Work on River Edge Subdivision, Lars Hoffman Crossing, Winter Ln., Winter Ct., Sunset Ct. and Sunset Dr. by Priority Line
  • Work on McPherson Ave., Douglas St. & Homer Ave. by Priority Line

The Week of 02/02/23 (Thursday)

  • Work on Godfrey Rd. (Stamper Ln. to Pearl St.) by Priority Line
  • Work on W. Delmar Ave., and D’Adrian Subdivision (D’Adrian Dr. & Seine Dr.) by Warren Construction
  • Work on River Edge Subdivision, Lars Hoffman Crossing, Winter Ln., Winter Ct., Sunset Ct. and Sunset Dr. by Priority Line

The Week of 01/26/23 (Will now start week on Thursday)

  • Work on Godfrey Rd. (Stamper Ln. to Pearl St.) by Priority Line
  • Work on W. Delmar Ave., and D’Adrian Subdivision (D’Adrian Dr. & Seine Dr.) by Warren Construction

The Week of 01/23/23

  • Work on Levis Lane Area (splicing fiber) by Warren Construction
  • Work on (pulling cables & splicing fiber in Briarwick Subdivision and Godfrey Rd.) by Millennium
  • Work on Godfrey Rd., Pearl St. (west side of railroad tracks), Lake Dr., Grace St., Squire St., Mulberry St., Ernest Dr., Franklin Ln., and Prairie St.) by Priority Line
  • Work on Wannamaker Ln., Greenwood Dr. & Chouteau Ave. by Millennium
  • Work on D’Adrian Subdivision by Warren Construction

The Week of 01/16/23

  • Work on Levis Lane Area (pulling cables & splicing fiber) by Warren Construction
  • Work on excavations on Godfrey Road (pulling cables & splicing fiber in Briarwick Subdivision) by Millennium
  • Work on Stamper Ln. & Belmont Village (Charmont Pl., Ladue Dr., Lafayette Ave., LaMotte Ln., Pardee Rd., Purvis Ln. and Vermont Pl.) by Priority Line
  • Work on Lexington Estates Dr., Keller St., Francis Dr. & Strong Ave. by Millennium
  • Work on D’Adrian Subdivision by Warren Construction

The Week of 01/09/23

  • Work on Levis Lane (pulling cables) by Warren Construction
  • Work on Godfrey Road by Millennium
  • Work on Tolle Ln., Belmont Village (Charmont Pl., Ladue Dr., Lafayette Ave., LaMotte Ln., Pardee Rd., Purvis Ln. and Vermont Pl.) & Godfrey Rd by Priority Line
  • Work on Pleasant Valley Dr., Homer Adams Pkwy & Strong Ave by Millennium

The Week of 01/02/23

  • Work on Levis Lane by Warren Construction
  • Work on Doral Dr., Hampton Ct., Cambridge Ct. & Avon Ct. by Millennium

The Week of 12/26/22

  • Work on Levis Lane by Warren Construction
  • Work on Enos Ln., Doral Dr., Hampton Ct. & Cambridge Ct. by Millennium

The Week of 12/19/22

  • Work on Levis Lane & Bryden Ln. by Warren Construction
  • Work on Godfrey Rd., Jackson Ln., Enos Ln., and Davis Pond Subdivision (Celesta St., Willis Ave., & Fleming Dr.) by Millennium

The Week of 12/12/22

  • Work on Levis Lane & Eagle Ridge Ct. by Warren Construction
  • Work on Godfrey Rd., Taylor Ave., and Celesta St. by Millennium

The Week of 12/05/22

  • Work on Levis Lane & Eagle Ridge Ct. by Warren Construction
  • Work on Godfrey Rd., Taylor Ave., and Thomas Dr. by Millennium

The Week of 11/28/22

  • Work on Levis Lane & Eagle Ridge Ct. by Warren Construction
  • Work on Godfrey Rd., Taylor Ave., and Thomas Dr. by Millennium

The Week of 11/21/22

  • Work on Levis Lane & Eagle Ridge Ct. by Warren Construction
  • Work on Godfrey Rd., Taylor Ave., and Thomas Dr. by Millennium

The Week of 11/14/22

  • Work on Highlands Rd. by Warren Construction
  • Work on Taylor Ave., Brian Dr., and Thomas Dr. by Millennium

The Week of 11/07/22

  • Work on Highlands Rd. by Warren Construction
  • Work on Taylor Ave., Brian Dr., and Thomas Dr. by Millennium

The Week of 10/31/22

  • Work on Levis Ln. by Warren Construction
  • Work on Robert Dr. by Millennium