Posted: Date 9/02/2010 The relocating of the manhole lids on St. Charles Drive will not be done until Tuesday, September 7, 2010 and Paving will start on St. Charles Drive on 09/08/10. We will be placing a oil prime with a sand coating on the soil cement work we hope will be done on Friday (inner loop) because we will not be able to water cure that area during this (forecast non rain) holiday weekend.
Posted: Date 9/02/2010 Because of the rain and wet conditions Dunn has canceled work for Thursday, September 2, 2010. Please pushed back your schedule another working day back. Dunn hopes to work on the soil cement in the inner loop of the Subdivision (St. Rose & St. Anthony Drives and St. Charles Drive from Bachman Lane to a little pass St. Rose Drive) and will start profiling the Cul-de-sacs and St. Charles Drive and may start relocating the manhole lids on St. Charles Drive on Friday, September 3, 2010. We apologize for any inconvenience that the weather and work has cause on to your lives this past week.
Attention: Date 9/01/2010 Dunn has canceled work for the 9/01/10 because of rain. So, the schedule has been pushed back another day. Dunn hopes to work on 9/02/10 weather permitting. Scheduled event will be soil cement in the inner loop of the Subdivision (St. Rose & St. Anthony Drives and St. Charles Dr. from Bachman Ln to a little pass St. Rose Dr.) and profiling the Cul-de-sacs and St. Charles Dr.
Attention: Date 8/24/2010 Dunn has informed us that their milling machine will be delayed by a day. The Pulverize schedule is as schedule. But all other stages will be set back by one day. The first day of removal will be on Friday 8/27 and the first day of Soil Cement will start on Monday 8/30. Profile Process first day will be 9/01 and the first day of Paving will start on 9/03. Sorry about the change.
Dunn Company and Charles Mahoney Company are starting a street reconstruction project in the Eastern half of the Villa Marie Subdivisions; streets included in project are St. John Dr., St. Charles Dr., St. Anthony Dr. and St. Rose Dr. The project is schedule to start on Wednesday, August 25th at 7:00 a.m. (Weather Permitting)
Schedule for the project can be found by hitting the Village Department tab then hit the Village Engineer link then hit the project link.